Contract
No: HK/2011/07 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-356/2009, Further
Evironmental permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009,
fep-05/356/2009, Fep-06/356/2009 and FEP-07/356/2009 Quarterly Environmental Monitoring
and Audit Report
- June 2014 to August 2014 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
22 September
2014 |
2.2 Scope
of the Project and Site Description
2.3 Division of the Project
Responsibility
2.4 Project Organization and Contact
Personnel
2.5 Principal
Work and Activities
4.2. Real Time Noise Monitoring Results
5.2. Real-time Noise Monitoring
5.6. Review
of the Reasons for and the Implications of Non-compliance
5.7. Summary
of action taken in the event of and follow-up on non-compliance
6. Complaints, Notification
of Summons and Prosecution
7. Cumulative Construction
Impact due to the Concurrent Projects.
lIST
OF TABLES
Table I Principal Work
Activities for Contract no. HK/2009/01
Table II Principal Work
Activities for Contract no. HK/2009/02
Table III Principal Work
Activities for Contract no. HY/2009/15
Table IV Principal Work Activities for Contract no. HK/2010/06
Table V Principal Work
Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract no. HK/2012/08
Table VII Principal
Work Activities for Contract no. HY/2010/08
Table 2.1 Schedule 2 Designated
Projects under this Project
Table 2.2 Details of Individual
Contracts under the Project
Table 2.3 Contact Details of
Key Personnel
Table 2.4 Principal Work Activities for Contract no. HK/2009/01
Table 2.5 Principal Work Activities for Contract no. HK/2009/02
Table 2.6 Principal Work
Activities for Contract no. HY/2009/15
Table 2.7 Principal Work
Activities for Contract no. HK/2010/06
Table 2.8 Principal Work
Activities for Contract no. HY/2009/19
Table 2.9 Principal Work Activities for Contract no. HK/2012/08
Table 2.10 Principal Work Activities for Contract no. HY/2010/08
Table 3.1 Noise Monitoring
Stations
Table 3.2 Real Time Noise
Monitoring Station
Table 3.3 Air Monitoring
Stations
Table 3.4 Marine Water Quality
Stations for Water Quality Monitoring
Table 3.5 Marine Water Quality
Monitoring Frequency and Parameters
Table
3.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 4.1 Noise Monitoring Station for Contract nos. HK/2009/01
and HK/2009/02 and HK/2010/06
Table 4.2 Noise Monitoring
Station for Contract nos. HY/2009/15
Table 4.3 Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.4 Real Time Noise
Monitoring Station for Contract no. HY/2009/11 and HY/2009/19
Table 4.5 Real Time
Noise Monitoring Station for Contract no. HY/2009/19
Table 4.6 Air Monitoring Stations for Contract no. HK/2009/01
Table 4.7 Air Monitoring Station for Contract no. HK/2009/02
Table 4.8 Air Monitoring Station
for Contract no. HY/2009/15
Table 4.9 Air Monitoring Stations for Contract no. HY/2009/19
Table 4.10 Water Monitoring
Stations for Contract no. HY/2009/11
Table 4.11 Water Monitoring Stations for Contract no. HK/2009/01
Table 4.12 Water Monitoring Stations for Contract no. HK/2009/02
Table 4.13 Water Monitoring Stations for Contract no. HK/2010/06
Table 4.15 Water Monitoring Stations for
Contract no. HY/2009/19
Table 4.15a Summary of
Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting period
Table 4.16 Summary of Water Quality
Monitoring Exceedances in Reporting period
Table 4.18 Details of Waste
Disposal for Contract no. HK/2009/01
Table 4.19 Details of Waste
Disposal for Contract no. HK/2009/02
Table 4.20 Details of Waste
Disposal for Contract no. HY/2009/15
Table 4.21 Details of Waste
Disposal for Contract no. HK/2010/06
Table 4.22 Details
of Waste Disposal for Contract no. HY/2009/19
Table 5.1 Summary of Water
Quality Monitoring Exceedances in Reporting period
Table 5.1a Summary of Enhanced
Dissolved Oxygen Monitoring Exceedances in Reporting period
Table 6.1 Cumulative Statistics
on Complaints
Table 6.2 Cumulative Statistics
on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1 Project Layout
Figure 2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Graphical Presentations
Appendix 4.2 Air Quality Monitoring Graphical
Presentations
Appendix 4.3 Water Quality Monitoring Graphical
Presentations
Appenidx 4.3a Additional Dissolved Oxygen
Monitoring Results
Appendix 4.4 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 7.1 Construction Programme of
Individual Contracts
Construction Activities for the
Reported Period
Table I Principal Work Activities for Contract
no. HK/2009/01
June 2014 |
July 2014 |
August 2014 |
Ongoing
demolition work of the exiting Expo Drive East Bridge Ongoing work
on UU diversion at Expo Drive East Bridge Ongoing
structure works for Stage 1 tunnel Ongoing Stage
2 excavation Installation
of pre-bored H-piles at HKCEC water channel Construction
of D-wall Ongoing
mainlaying work on discharge cooling and saltwater Ongoing
rectification work Demolition
work of exiting HKCEC pump house |
Rock trimming works |
Rock
trimming works |
Table II Principal Work Activities for Contract no.
HK/2009/02
June 2014 |
July 2014 |
August 2014 |
Road works
between Expo Drive and Expo Drive East Backfilling
work Installation
and testing of AVR Defect
rectification works in WSD Salt Water Pumping Station ABWF Works(
Completion of fender system panels installation) E&M Works
for instance fire services ducting and cabling works VSD
installation and testing of movable ramp and life cage Ongoing
capping beam construction Removal of
marine mud at WCR2 Erection of
Bridge 3 Modification
of D-Wall for Bridge 2
Delivery of fabricated temp bridges |
Road works
between Expo Drive and Expo Drive East Backfilling
work Defect
rectification works in WSD Salt Water Pumping Station ABWF Works in
Section VIIIA E&M Works
for instance fire services ducting and cabling works Capping beam
construction Installation
of seawall block Removal of
marine mud and reclamation at WCR2 Temporary
drainage construction
Concrete decking |
Road works Connection
works of temporary sewage pipe Lighting
installation Granolithic
finishing Reclamation at
WCR2 Excavation
works
Construction of at-grade road |
Table III
Principal Work Activities for
Contract no. HY/2009/15
June 2014 |
July 2014 |
August 2014 |
·
EVA construction at Eastern Breakwater ·
Reinstatement of Eastern Breakwater ·
Removal of Seawall Blocks at TS2, TPCWAE
& TS4 ·
Demolition of D-Wall at TS2, TPCWAE &
TS4 ·
Maintenance dredging
|
·
EVA construction at Eastern Breakwater ·
Reinstatement of Eastern Breakwater ·
Removal of Seawall Blocks at TS2, TPCWAE
& TS4 ·
Demolition of D-Wall at TS2, TPCWAE &
TS4 ·
Maintenance dredging
|
·
EVA construction at Eastern Breakwater ·
Reinstatement of Eastern Breakwater ·
Removal of Seawall Blocks at TPCWAE &
TS4 ·
Demolition of D-Wall at TS2, TPCWAE &
TS4 ·
Underwater Cutting of Temporary Diaphragm
Walls at TS2, TS4 and TPCWAE |
Table IV Principal
Work Activities for Contract no. HK/2010/06
June 2014 |
July 2014 |
August 2014 |
Nil |
Nil |
Nil |
Table V Principal Work Activities for Contract no.
HY/2009/19
June 2014 |
July 2014 |
August 2014 |
Road works at Watson Road
Bored piling (Land)
Removal/Installation of strut at ELS Construction of Dolphin Cap ELS for Cut &Cover Tunnel and EVB Laying of 1500f pipe Launching of segments Extraction of temporary pile from
marine section Construction of bridge TA1 Pre-bored H-pile for Admin. Building
continue U-beam installation continue Parapet construction continue Wing slab extension for segment
continue Construction of TD bridge continue Construction of Bridge E Construction of Bride F4 and F5 |
Construction of Dolphin Cap
Extraction of temporary pile from marine section |
Construction of Dolphin Cap |
Table VI Principal
Work Activities for Contract no. HK/2012/08
June 2014 |
July 2014 |
August 2014 |
ELS for box
culvert La at Lung King Street Filling for
seawall rock mound formation Filling for
reclamation Dredging |
ELS for box
culvert La at Lung King Street Filling for
seawall rock mound formation Filling for reclamation |
ELS for box
culvert La at Lung King Street Filling for
seawall rock mound formation Filling for
reclamation Dredging
|
Table
VII
Principal Work Activities for Contract
no. HY/2010/08
June 2014 |
July 2014 |
August 2014 |
Rock filling
works (works cease on 8th Feb. 2014) |
Rock filling
works (works cease on 8th Feb. 2014) Dredging works |
Rock filling
works Dredging works Seawall blocks
installation |
Noise Monitoring
Real-time Noise Monitoring
Air Quality Monitoring
Water Quality Monitoring
WQM during flood tide was cancelled on 1 August 2014
WQM during ebb tide was cancelled on 13 August 2014
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-02/356/2009,
FEP-03/356/2009,
FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009 to
implement the Environmental Monitoring and Audit (EM&A) programme as
stipulated in the EM&A Manual of the approved Environmental Impact
Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved
EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link
(Register No. AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.4 of EM&A Manual and “Environmental
Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
during the period from June 2014 to August 2014.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested east-west Connaught Road Central/Harcourt Road / Gloucester Road
Corridor (the Corridor) which is currently operating beyond its capacity. The
CWB will provide relief to the existing congestion along the Corridor and cater
for the anticipated growth of traffic on Hong Kong Island. Without the CWB and
its access roads, there will not be sufficient capacity to serve the heavy
traffic demands at both strategic and local levels.
2.2.1.
The
Project is located mainly in Wan Chai North, Causeway Bay and North Point, and
is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick
Pier Street to the west and Tong Shui Road Interchange to the east, as shown in
Figure 2.1.
2.2.2.
The
study area encompasses existing developments along the Wan Chai, Causeway Bay
and North Point shorelines. Major land uses include the Hong Kong Convention
& Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan
Chai Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club
(RHKYC), the Police Officers' Club, the Causeway Bay Typhoon Shelter (CBTS) and
commercial and residential developments.
2.2.3.
The scope of the Project comprises:
·
Land formation for key transport infrastructure and
facilities, including the Trunk Road (i.e. CWB) and the associated slip roads for
connection to the Trunk Road and for through traffic from Central to Wan Chai and
Causeway Bay. The land formed for the above transport infrastructure will provide
opportunities for the development of an attractive waterfront promenade for the
enjoyment of the public
·
Reprovisioning / protection of the existing
facilities and structures affected by the land formation works mentioned above
·
Extension, modification, reprovisioning or
protection of existing storm water drainage outfalls, sewerage outfalls and
watermains affected by the revised land use and land formation works mentioned
above
·
Upgrading of hinterland storm water drainage system
and sewerage system, which would be rendered insufficient by the land formation
works mentioned above
·
Provision of the ground level roads, flyovers,
footbridges, necessary transport facilities and the associated utility services
·
Construction of the new waterfront promenade,
landscape works and the associated utility services
·
The Trunk Road (i.e. CWB) within the study area and
the associated slip roads for connection to the Trunk Road.
2.2.4.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits (FEP) such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The
details of individual contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II – Central –Wanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central – Wan Chai Bypass – North
Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
10 March 2014 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai
Development Phase II Central- Wan Chai Bypass at
Wan Chai West |
DP1,DP2,
DP3 |
5 March 2013 |
HY/2011/08 |
Central-Wan
Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works
Associated with Tunnel Commissioning |
DP1 |
To be commenced tentatively on 4th quarter
in 2014 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for
WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint
Venture Board Representative |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Deputy Site
Agent |
Mr Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr Kenneth
Chan |
9160 3850 |
|||
Senior Environmental Engineer |
Ms. Wendy Ng |
9803 0057 |
|||
Assistant
Environmental Engineer |
Miss.
Connie Chan |
6157 7057 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project
Manager |
Mr. Alfred Leung |
3658-3022 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
K C Cheung |
3557 6399 |
2566 2192 |
Site Manager |
J H Chen |
3557 6368 |
|||
|
|
Contractor’s Representative |
Andrew Wong |
3557 6358 |
|
|
|
Contractor’s Representative |
Gene Cheung |
3557 6395 |
|
|
|
Senior Project Manager |
Eddie Tang |
35576452 |
|
Environmental Officer |
Mr. Daniel Sin |
3557 6347 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Eric
Yip |
2529 2068 |
|||
Environmental Officer |
Clement
Pang |
9735 9200 |
|||
Environmental
Supervisor |
Jacky
Cheung |
9779 2292 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Eric Yip |
252902068 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project Director |
Andrew Tse |
9137 1811 |
2877 1522 |
Project Manager |
Victor Wu |
9193 8871 |
|
||
Deputy Project Manager |
George Cheung |
9268 1918 |
|
||
Site Agent |
Paul Lui |
9095 7922 |
|
||
Environmental Officer |
James Ma |
9130 9549 |
|
||
Environmental Supervisor |
Ching Man, Chan |
6050 4919 |
|
||
China State |
Contractor under
Contract no. HY/2010/08 |
Project Director |
Cheung Kit Cheung |
3557 6399 |
2566 8061 |
|
|
Project Manager |
Chan Ying Lun |
3418 3001 |
|
|
|
Deputy Project Manager |
Chris Leung |
3467 4299 |
|
|
|
Site Agent |
Dave Chan |
3467 4277 |
|
|
|
Environmental Officer |
C.M. Wong |
3557 6464 |
|
|
|
Environmental
Supervisor |
Desmond Ho Tsz Ho |
3557 6466 |
|
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
34652888 |
34652899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
During
this reporting period, the principal work activities for Contract no.
HK/2009/01 are summarized in Table 2.4.
Table
2.4 Principal Work Activities for Contract no.
HK/2009/01
June 2014 |
July 2014 |
August 2014 |
Ongoing
demolition work of the exiting Expo Drive East Bridge Ongoing work
on UU diversion at Expo Drive East Bridge Ongoing
structure works for Stage 1 tunnel Ongoing Stage
2 excavation Installation
of pre-bored H-piles at HKCEC water channel Construction
of D-wall Ongoing
mainlaying work on discharge cooling and saltwater Ongoing
rectification work Demolition
work of exiting HKCEC pump house |
Rock trimming works |
Rock
trimming works |
2.5.2.
During
this reporting period, the principal work activities for Contract no.
HK/2009/02 are summarized in Table 2.5.
Table
2.5 Principal Work Activities for Contract no.
HK/2009/02
June 2014 |
July 2014 |
August 2014 |
Road works
between Expo Drive and Expo Drive East Backfilling
work Installation
and testing of AVR Defect
rectification works in WSD Salt Water Pumping Station ABWF Works(
Completion of fender system panels installation) E&M Works
for instance fire services ducting and cabling works VSD
installation and testing of movable ramp and life cage Ongoing
capping beam construction Removal of
marine mud at WCR2 Erection of
Bridge 3 Modification
of D-Wall for Bridge 2
Delivery of fabricated temp bridges |
Road works
between Expo Drive and Expo Drive East Backfilling
work Defect
rectification works in WSD Salt Water Pumping Station ABWF Works in
Section VIIIA E&M Works
for instance fire services ducting and cabling works Capping beam
construction Installation
of seawall block Removal of
marine mud and reclamation at WCR2 Temporary
drainage construction
Concrete decking |
Road works Connection
works of temporary sewage pipe Lighting
installation Granolithic
finishing Reclamation at
WCR2 Excavation
works
Construction of at-grade road |
2.5.3.
Major construction activities for Contract no.
HY/2009/15 was commenced on 10 November 2010. During this reporting period, the
principal work activities for Contract no. HY/2009/15 are summarized as below:
Table
2.6 Principal Work Activities for Contract no. HY/2009/15
June 2014 |
July 2014 |
August 2014 |
·
EVA construction at Eastern Breakwater ·
Reinstatement of Eastern Breakwater ·
Removal of Seawall Blocks at TS2, TPCWAE
& TS4 ·
Demolition of D-Wall at TS2, TPCWAE &
TS4 ·
Maintenance dredging |
·
EVA construction at Eastern Breakwater ·
Reinstatement of Eastern Breakwater ·
Removal of Seawall Blocks at TS2, TPCWAE
& TS4 ·
Demolition of D-Wall at TS2, TPCWAE &
TS4 ·
Maintenance dredging |
·
EVA construction at Eastern Breakwater ·
Reinstatement of Eastern Breakwater ·
Removal of Seawall Blocks at TPCWAE &
TS4 ·
Demolition of D-Wall at TS2, TPCWAE &
TS4 ·
Underwater Cutting of Temporary Diaphragm
Walls at TS2, TS4 and TPCWAE |
2.5.4.
Contract
no. HK/2010/06 was commenced on 22 March 2011. During this reporting period,
the principal work activities for Contract no. HK/2010/06 are summarized as
below:
Table
2.7 Principal Work Activities for Contract no. HK/2010/06
June 2014 |
July 2014 |
August 2014 |
Nil |
Nil |
Nil |
2.5.5.
Contract no. HY/2009/19 was commenced on 24 March
2011. During this reporting period, the principal work activities for Contract
no. HY/2009/19 are summarized as below:
Table
2.8 Principal Work Activities for Contract no. HY/2009/19
June 2014 |
July 2014 |
August 2014 |
Road works at Watson Road Bored piling (Land) Removal/Installation of strut at ELS
Construction of Dolphin Cap
ELS for Cut &Cover Tunnel and EVB
Laying of 1500f pipe
Launching of segments
Extraction of temporary pile from marine section
Construction of bridge TA1
Pre-bored H-pile for Admin. Building continue
U-beam installation continue
Parapet construction continue
Wing slab extension for segment continue
Construction of TD bridge continue
Construction of Bridge E
Construction of Bride F4 and F5 |
Construction of Dolphin Cap
Extraction of temporary pile from marine section |
Construction of Dolphin Cap |
2.5.6.
Contract no. HK/2012/08 was commenced on March 2013.
During this reporting period, the principal work activities for Contract no. HK/2012/08
are summarized as below:
Table
2.9 Principal Work Activities for Contract no. HK/2012/08
June 2014 |
July 2014 |
August 2014 |
ELS for box
culvert La at Lung King Street Filling for
seawall rock mound formation Filling for
reclamation Dredging |
ELS for box
culvert La at Lung King Street Filling for
seawall rock mound formation Filling for reclamation |
ELS for box
culvert La at Lung King Street Filling for
seawall rock mound formation Filling for
reclamation Dredging |
2.5.7.
Contract no. HY/2010/08 was commenced on 21 March
2013. During this reporting period, the principal work activities for Contract
no. HY/2010/08 are summarized as below:
Table 2.10 Principal Work Activities for
Contract no. HY/2010/08
June 2014 |
July 2014 |
August 2014 |
Rock filling
works (works cease on 8th Feb. 2014) |
Rock filling
works (works cease on 8th Feb. 2014) Dredging works |
Rock filling
works Dredging works Seawall blocks
installation |
2.5.8.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
Noise Monitoring Stations
3.1.1. The noise monitoring stations for the Project
are listed and shown in Table 3.1 and Figure 3.1. Appendix 3.1 shows the established Action/Limit
Levels for the monitoring works.
Table
3.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church
Henrietta Secondary School |
Real
time Noise Monitoring Stations
3.1.2. The real-noise monitoring
stations for the Project are listed and shown in Table 3.2 and Figure
3.1. Appendix
3.1 shows the established
Action/Limit Levels for the monitoring works.
3.1.3. The
real-time noise monitoring at RTN2-Oil Street Community Liaison Centre has been
relocated to City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct
2012, which is a representative of noise sensitive receiver- City Garden. The
baseline noise level of RTN2a will adopt the results derived from the baseline
noise monitoring conducted in Electric Centre from 4 December 2009 to 17
December 2009.
3.1.4. As the
land-based piling and filling works- DP3 at Tin Hau had been completed on 3
September 2012 and confirmed by RSS, the real-time noise monitoring results at RTN1
- FEHD Hong Kong Transport Section Whitfield Depot was excluded under
EP-356/2009 since 28 November 2012.
Table
3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
l
Real time noise monitoring results and
graphical presentation during night time period are for information only.
l
RTN2 had been
relocated to RTN2a since 5 Oct 2012
Noise Monitoring
Parameters, Frequency and Duration
3.1.5. The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period
between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq
(5 minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.6. Noise monitoring shall be
carried out at all the designated monitoring stations. The monitoring frequency
shall depend on the scale of the construction activities. The following is an
initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
·
one
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.7. If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays, additional
weekly impact monitoring shall be carried out during respective restricted
hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
3.1.8. Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 hours daily basis when
noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
Monitoring Equipment
3.1.9. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level meters
in compliance with the International Electrotechnical Commission Publications
651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for
carrying out the noise monitoring. Immediately prior to and following each
noise measurement the accuracy of the sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.10. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
3.2.1.
The
air monitoring stations for the Project are listed and shown in Table
3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the
monitoring works.
Table 3.3 Air Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to Pedestrian Plaza |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
* Remarks: As per the ENPC
meeting in January 2011, the monitoring stations CMA3a - Future CWB site office
at Wanchai Waterfront Promenade and CMA6a - Future AECOM site office at Work
Area were renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
3.2.4.
For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5 High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
·
0.6
- 1.7 m3 per minute adjustable flow range;
·
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable
of providing a minimum exposed area of 406 cm2;
·
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
equipped
with a shelter to protect the filter and sampler;
·
incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
equipped
with a flow recorder for continuous monitoring;
·
provided
with a peaked roof inlet;
·
incorporated
with a manometer;
·
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
easily
changeable filter; and
·
capable
of operating continuously for a 24-hour period.
3.2.6 Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement /
Analysis
3.2.7 A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
3.2.8 An
alternative non-HOKLAS
accredited laboratory was set-up for carrying out the laboratory
analysis, the laboratory equipment was approved by the ER on 8
February 2011 and
the measurement procedures were witnessed by the IEC. Any measurement performed by
the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall
regularly audit to the measurement performed by the laboratory to ensure the
accuracy of measurement results.
3.2.9 Filter
paper of size 8" x 10" shall be labelled before sampling. It shall be
a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
3.2.10 After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
3.2.11 All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for
odour patrol
3.2.12 Odour patrols along the
shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai Public Cargo Working
Area when there is temporary reclamation in Causeway Bay Typhoon Shelter and/or in the ex-Wan Chai Public Cargo
Working Area, or when there is dredging of the odorous sediment and slime at
the south-western corner of the Causeway Bay Typhoon Shelter. Odour patrols
will be carried out at bi-weekly intervals during July, August and September by
a qualified person of the ET who shall:
·
be
at least 16 years of age;
·
be
free from any respiratory illnesses; and
·
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
·
before
and during odour patrol
3.2.13 Odour patrol shall be conducted by independent
trained personnel / competent persons patrolling and sniffing around the shore
as shown in Figure 3.1 to detect any odour at
the concerned hours (afternoon is preferred for higher daily temperature).
3.2.14 The qualified person will use the nose (olfactory
sensor) to sniff odours at different locations. The main odour emission sources
and the areas to be affected by the odour nuisance will be identified.
3.2.15 The perceived odour intensity is to be divided into
5 levels which are ranked in the descending order as follows:
·
0 -
Not detected. No odour perceived or an odour so weak that it cannot be easily
characterized or described;
·
1 -
Slight Identifiable odour, and slight chance to have odour nuisance;
·
2 -
Moderate Identifiable odour, and moderate chance to have odour nuisance;
·
3 -
Strong Identifiable, likely to have odour nuisance;
·
4 -
Extreme Severe odour, and unacceptable odour level.
3.2.16 The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 3.1.
3.3.1. The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the construction
phase. Marine water quality monitoring
for dissolved oxygen (DO), suspended solid (SS) and turbidity is therefore
recommended to be carried out at selected WSD flushing water intakes. The impact monitoring should be carried out
during the proposed dredging works to ensure the compliance with the water
quality standards.
3.3.2. The
updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by
EPD on 29
Water Quality Monitoring Stations
3.3.3. It is proposed to monitor the water quality at 2
WSD salt water intakes and 8 cooling water intakes along the seafront of the
Victoria Harbour. The proposed water quality monitoring stations of the Project
are shown in Table 3.4 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.4
Marine Water Quality Stations for Water
Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C7 |
Windsor House |
837193.7 |
816150.0 |
P1 |
HKCEC
Phase I |
835774.7 |
816179.4 |
P3 |
The Academy of performing Arts |
835824.6 |
816212.0 |
P4 |
Shui on Centre |
835865.6 |
816220.0 |
P5 |
Government
Buildings (Wanchai
Tower / Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
RW21-P789 |
Great
Eagle Centre/ Sun Hung Kai Centre/CWB |
836268.0 |
816020.0 |
Remarks: - The cessation of
seawater intake operation for C6 was confirmed on 17 May 2011, the water
monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect
to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at WSD9,
WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 water quality monitoring were
temporarily suspended from 27 Apr 2012.
- C5e and C5w water quality monitoring station
was temporarily suspended since 29 July 2013
- C2, C3 C4e and C4w water quality monitoring
station was temporarily suspended since 24 Apr 2013
Water Quality Parameters
and frequency
3.3.4. Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
3.3.5. In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal stage,
and any special phenomena and work underway at the construction site etc.
3.3.6. The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table 3.5 shows the proposed
monitoring frequency and water quality parameters. Duplicate in-situ measurements and water
sampling should be carried out in each sampling event. For selection of tides for in-situ
measurement and water sampling, tidal range of individual flood and ebb tides
should be not less than 0.5m.
Table
3.5 Marine Water Quality Monitoring Frequency
and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1. For
selection of tides for in-situ measurement and water sampling, tidal range of
individual flood and ebb tides should be not less than 0.5m.
2.
Turbidity should be
measured in situ whereas SS should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
3.3.7. The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
·
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
·
a
temperature of 0-45 degree Celsius
3.3.8. It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
3.3.9. Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement
Instrument
3.3.10 The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach
model 2100P or an approved similar instrument).
Sampler
3.3.11 Water sampler comprises a transparent PVC
cylinder, with a capacity of not less than 2 litres, and can be effectively
sealed with latex cups at both ends. The sampler should have a positive
latching system to keep it open and prevent premature closure until released by
a messenger when the sampler is at the selected water depth (e.g. Kahlsico
Water Sampler or an approved similar instrument).
Sample Container and
Storage
3.3.12 Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4°C without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
3.3.13 A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
3.3.14 A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position
Equipment
3.3.15 A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ
Instruments
3.3.16 All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
3.3.17 For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
3.3.18 Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
Laboratory Measurement /
Analysis
3.3.19 Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
Causeway Bay Typhoon Shelter
3.3.20 The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
3.3.21 Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table
3.6 and Figure 3.1.
Table 3.6 Marine
Water Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior Hotel |
C7 |
Windsor House |
Ex-WPCWA-SW |
South-western of the ex-Wan Chai
Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern of the ex-Wan Chai
Public Cargo Working Area |
3.3.22 The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be less than 3m, only the
mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
3.3.23 During
dredging of the sediment at the south-western corner of the Causeway Bay
Typhoon Shelter, daily monitoring of suspended solids and 24 hour monitoring of
turbidity at the cooling water intakes (C6 and C7) shall be conducted.
3.3.24 The 24
hours monitoring of turbidty at the cooling water intakes (C6 and C7) shall be
established by setting up a continuous water quality monitoring station in
front of the intakes during the dredging activities. The monitoring system include the turbidity
sensor and data logger which is capable of data capturing at every 5 minutes.
The data shall be downloaded daily and compared with the Action and Limit level
determined during the baseline water qualtiy monitoring at the cooling water
intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
3.3.25 In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
3.3.26 With
respect to the commencement of dredging works under HK/2012/08 and the
installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since 24 July 2013
3.3.27 The
monitoring of dissolved oxygen are to be carried out once per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
4.0.1. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure 2.1 and
Figure
3.1. The monitoring results are presented in according to the
Individual Contract(s).
4.0.2 The
major work activities for Contract no. HY/2009/11 was confirmed substantial
complete by RSS on 4 January 2012. The FEP surrender application
was submitted to EPD by contractor on 16 Jan 2012 that they would
surrender the permit on 1 Jan 2012. Moreover, the construction site was
handed over to contractor HY/2009/19 on 4 January 2012. However, the surrender
of the FEP for HY/2009/11 withdrew by contractor on 14 February 2012 due to
some outstanding works was confirmed by RSS on 10 Feb 2012.
Therefore, the noise, air and water quality monitoring were keeping in
view for the commencement of the works under this
contract. No construction activity was conducted by HY/2009/11 up to 4 January 2012.
4.0.3 According to
EP-364/2009/A Part B, “Scale and Scope of Designated Project”, Remarks (c),”The
permanent and temporary reclamation and associated dredging works related to
the CWB construction are separately covered by environmental permit No. EP-356/2009
issued to Civil Engineering and Development Department”, and marine piling
works to be conducted by the Contractor of Contract no. HY/2009/19 from 28
January 2012 was considered to be governed under EP-356/2009. As the
construction site area of Contract no. HY/2009/11 had already been handed over
to Contract no. HY/2009/19, the designated noise, water and air quality
monitoring stations for Contract no. HY/2009/11 would be shared with Contract
no. HY/2009/19 from 28 January 2012.
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC and Contract no. HK/2009/02 - Wan
Chai Development Phase II – Central – Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II – Central-Wan Chai Bypass over MTR
Tsuen Wan Line
4.1.1.
The
proposed divisions of noise monitoring stations are summarized in Table
4.1 below.
Table 4.1 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.2. No action or limit level exceedance was
recorded in June, July and August reporting months. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section)
4.1.3. The noise monitoring for HY/2009/15 was
commenced on 10 November 2010. The
proposed division of noise monitoring stations are summarized in Table
4.2 below.
Table
4.2
Noise Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.4.
One limit level
exceedance was recorded on 24 June 2014 at M2b – Noon
Day Gun Area in June reporting month.
4.1.5.
Concrete breaking works at TS4 under HY/2009/15 were observed during
monitoring on 24 June 2014. It was considered that the concrete breaking works
was the major noise contribution. As such, the limit level exceedance was
concluded as project related. Rectification measures including provision of
noise blanket for breakers was implemented by the contractor. Additional
monitoring was conducted and no exceedance was identified.
4.1.6.
No action or limit level exceedance was recorded in July reporting
month.
4.1.7.
One limit level exceedance was recorded on 5 August 2014 at M2b – Noon
Day Gun Area in August reporting month. Barge operation and concrete breaking works at TS4 under HY/2009/15 were
observed during monitoring on 5 August 2014. It was considered that the
operation of derrick barge and nearby breaking works at TS4 were the major
noise contribution. As such, the limit level exceedance was concluded as
project related. Rectification measures including provision of noise blanket
for breakers and provision of noise screen for engine at the derrick barrage
were implemented by the contractor. Additional monitoring was conducted and no
exceedance was identified.
4.1.8.
Details
of noise monitoring results and graphical presentation can be referred in Appendix 4.1
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.1.9.
Noise
quality monitoring at M4b and M5b have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 2012.
4.1.10.
The
proposed division of noise monitoring stations for Contract no. HY/2009/19 are
summarized in Table 4.3 below:
Table 4.3
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
4.1.11.
Four limit level exceedances were recorded on 5, 10, 17
and 25 June 2014 at M6 – HK Baptist Church Henrietta
Secondary School in June reporting month. Major traffic noise observed during
monitoring on 5, 10, 17 and
25 June 2014 and it was considered as the major
noise contribution. As such, the limit level exceedances were concluded as
non-project related.
4.1.12.
No action or limit level exceedance was recorded
in July reporting month.
4.1.13.
One limit level exceedance was recorded on 28
July 2014 at M6 – HK Baptist Church Henrietta Secondary School in August
reporting month. Major traffic noise observed during monitoring on 28 July 2014
and it was considered as the major noise contribution. As such, the limit level
exceedance was concluded as non-project related.
4.1.14.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of graphical
presentation can be referred in Appendix
4.1.
Contract
no. HY/2010/08-Central-Wanchi Bypass Tunnel (Slip Road 8 Section)
4.1.15.
The proposed division of noise monitoring
stations are summarized in Table 4.4
below.
Table 4.4 Noise Monitoring Station for Contract no. HY/2010/08
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.16.
No action or limit exceedance was recorded in
June, July and August reporting months.
4.1.17.
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.2.1 As the land-based piling
and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and
confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong
Transport Section Whitfield Depot was excluded under EP-356/2009 since 28
November 2012.
4.2.2 The real-time noise
monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to
City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a
representative of noise sensitive receiver- City Garden. The baseline noise
level of RTN2a will adopt the results derived from the baseline noise
monitoring conducted in Electric Centre from 4 December 2009 to 17 December
2009.
4.2.3 The major work activities
for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4
January 2012. The construction site was handed over to contractor HY/2009/19 on
31 December 2011 and the FEP-01/356/2009 was surrendered on 22 Oct 2012.
4.2.4 Real-time
noise monitoring at FEHD Hong Kong Transport Section Whitfield Depot commenced
external wall renovation since 1 June 2012
Table 4.5
Real Time Noise Monitoring Station for Contract no.
HY/2009/19
District |
Station |
Description |
North Point |
RTN2a |
Electric Centre |
l Real
time noise monitoring results and graphical presentation during night time
period are for information only.
l
RTN2 had been relocated to RTN2a since 5 Oct 2012
l
RTN1 monitoring had been finished on 28 Nov 2012
4.2.5 Limit level
exceedances were recorded at RTN2a-Electric Centre during restricted hours on 8
June 2014 and during daytime on 20 June 2014 in June reporting month. After
checking with Contractor, no construction activity was conducted at the
concerned location on 8 June 2014 during the recorded period and the
exceedances were considered to be contributed by the adverse weather condition
during the hoisting period of rainstorm signal. On 20 June 2014, despite socket
H-piling and bored piling activities were conducted at the concerned location
on the monitoring day, contractor mitigation measures including erection of
temporary noise barrier was in place. Also, piling works was also observed at
nearby non-CWB Projects. In view of the exceedance was non-continuous, it was
considered that the exceedance was considered as non-project related
4.2.6
Limit level exceedances were recorded at
RTN2a-Electric Centre during restricted hours on 27 July 2014 and during
daytime on 22 July 2014 in July reporting month. After checking with
Contractor, despite socket H-piling was conducted at the concerned location on
22 July 2014 during the recorded period, contractor mitigation measures
including erection of temporary noise barrier was in place and the exceedance
was considered to be contributed by the adverse weather condition during the
hoisting period of rainstorm signal. On 27 July 2014, no construction activity
was conducted at the concerned location during the monitoring period. As such,
it was considered that the exceedance was considered as non-project related and
considered to be contributed by nearby IEC traffic.
4.2.7 Limit level
exceedances were recorded at RTN2a-Electric Centre during daytime on 5, 13, 16,
21 and 23 August 2014 and during restricted hours on 1 August 2014 in August
reporting month. After checking with Contractor, bored piling was conducted at
the concerned location on 5, 13 and 16 during the recorded period and bored
piling and breaking works was conducted on 21 and 23 August 2014, contractor
mitigation measures including erection of temporary noise barrier was in place.
In view of the exceedances are non-continuous, the exceedances are considered
to be non-project related and contributed by nearby IEC traffic. On 1 August
2014, bored piling was conducted at the concerned location during the
monitoring period. Temporary noise barrier was implemented by the Contractor
and the CNP GW-RS0752-14 was in place and complied. The exceedance was considered
as non-project related and considered to be contributed by nearby IEC traffic.
4.3.1.
1hr and 24hr TSP monitoring were conducted at
CMA1b, CMA2a, CMA3a, CMA4a, CMA5a and CMA6a in the reporting period.
Contract no. HY/2009/11 – Central – Wanchai Bypass,
North Point Reclamation
4.3.2.
The major work activities for Contract no.
HY/2009/11 was confirmed substantial complete by RSS on 4 January 2012. The
construction site was handed over to contractor HY/2009/19 and the FEP-01/356/2009
was surrendered on 22 October 2012. The monitoring for the contract was
temporary suspended on 6 January 2012.
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
4.3.3.
Air
monitoring was commenced on 1
Table
4.6 Air Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
WDII PRE Site Office * |
4.3.4. No action
or limit exceedance was recorded in June, July and August reporting months.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.3.5.
Air
monitoring was commenced in mid-January 2011 for the land-filling work for
Contract no. HK/2009/02. The proposed division of air monitoring stations is
summarized in Table 4.7 below.
Table
4.7 Air Monitoring Station
for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.6.
No
action or limit level exceedance was recorded in June, July and August
reporting months.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section)
4.3.7.
Air
monitoring was commenced on 15 March 2011 for the land filling work for
Contract no. HY/2009/15. The proposed division of air monitoring
stations are summarized in Table 4.8 below.
Table 4.8
Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
4.3.8. No action
or limit exceedance was recorded in June, July and August reporting months.
4.3.9.
The odour patrol along the odour route with 7
sniffing locations was conducted by a qualified odour patrol member on 8, 22 July and 5, 19 August at the concerned hours (afternoon for higher
daily temperature). No action or limit exceedance was recorded in July and
August reporting months.
Contract no. HY/2009/19 –Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.3.10.
Air monitoring at CMA1b and CMA2a have been
implemented with respect to HY/2009/19 since the marine bore piling works
started on 28 Jan 2012. No exceedance was recorded in the reporting
period.
4.3.11.
The proposed division of air monitoring stations is
summarized in Table 4.9 below.
Table
4.9 Air
Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
4.3.12. No
exceedance was recorded in June, July and August reporting months.
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
4.4.1.
Water quality monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
is summarized in Table 4.10 below.
4.4.2.
Water quality monitoring station RW21-P789 has been
implemented with respect to HK/2009/02 started on 29 July 2013.
Table 4.10 Water Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
-
WSD7
and WSD20 water quality monitoring were temporarily suspended since 27 Apr
2012.
-
C2,
C3 C4e and C4w water quality monitoring station was temporarily suspended since
24 Apr 2013
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II – Central – Wan Chai Bypass at WanChai East
4.4.3.
Water
quality monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010.
The proposed division of water monitoring stations is summarized in Table
4.11 below.
Table 4.11 Water Monitoring Stations for Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
|||
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
|||
Cooling Water Intake |
||||||
RW21-P789 |
Great Eagle Centre/ Sun Hung Kai Centre/CWB |
836268.0 |
816020.0 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to
HK/2009/02 from 8 Feb 2012.
-
C5e
and C5w water quality monitoring station was temporarily suspended since 29
July 2013
Contract
no. HK/2012/08 - Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
4.4.4.
Water
monitoring for Contract no. HK/2012/08 was commenced on 5 March 2013. The
proposed division of water monitoring stations are summarized in Table 4.12
below.
Table
4.12
Water Monitoring Stations for Contract
no. HK/2012/08
Station Ref. |
Location |
Easting |
Northing |
|
WSD Salt Water Intake |
||||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
|
Cooling Water Intake |
||||
P1 |
HKCEC Phase I |
835774.7 |
816179.4 |
|
P3 |
The Academy of
performing Arts |
835824.6 |
816212.0 |
|
P4 |
Shui on Centre |
835865.6 |
816220.0 |
|
P5 |
Government Buildings (Wanchai Tower /
Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
|
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section)
4.4.5. As the removal of reclamation work
of TS1 at CBTS has been completed, all procedures have been rectified and
complied with the conditions set in EP-356/2009 and FEP-04/356/2009.
4.4.6.
Due to the presence of obstacle within the inner silt curtain frame at
sampling point, water quality point at C7 was finely adjusted to the outside of
the inner silt curtain frame since 29 Dec 2012.
4.4.7.
Due to the commencement of the
maintenance dredging on 10 November 2010, water quality monitoring for Contract
no. HY/2009/15 was commenced on 9 November 2010. The proposed division of water
monitoring stations is
summarized in Table 4.13 below.
Table
4.13 Water Monitoring Stations for Contract no.
HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C7 |
Windsor
House |
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation for C6 was
confirmed on 17 May 2011, the water monitoring at C6 was then terminated since
17 May 2011.
Contract no. HY/2009/19 – Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
4.4.8. Due to the
commencement of the marine bored piling on 28 Jan 2012, water quality
monitoring for Contract no. HY/2009/19 was commenced on 28 Jan 2012.
4.4.10.
As confirmed by CWB RSS, the marine pilling works under contract
HY/2009/19 was confirmed completed by 4 March 2013. The water quality monitoring at the
respective monitoring stations C8 and C9 were temporarily suspended since 30
March 2013.
4.4.11.
Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no
water deterioration with respect to NPR was commenced since 7 Jan 2012 and it
was completed on 6 February 2012.
4.4.12.
Water quality monitoring at WSD10 and WSD15 was temporary suspended
while water quality monitoring at WSD9 and WSD17 was implemented with respect
to HK/2009/02 from 8 Feb 12 onwards;
4.4.13.
Water quality monitoring at C8 and C9 have been implemented with respect
to HY/2009/19 since the marine bore piling work started on 28 Jan 12.
4.4.14.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Center (C9) between 9 January
2012 to 30 July 2012 which caused to the inaccessibility of sampling either
land and marine since 3 Feb 2012, there is a fine adjustment of the sampling
location of water quality monitoring at C9 since 10 March 2012 to the closest
accessible point prior to the completion of the external façade refurbishment
work.
4.4.15.
With respect to the trial dredging at WCR2 was scheduled on 20, 22, 24,
25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water
quality monitoring results at WSD21 during this period was checked and
indicated that there was no contribution due to the trial dredging
operation. Enhanced review of water quality around WCR2 was also
implemented and no deterioration in the water quality was observed.
4.4.16. Due to the access of water monitoring station at WSD19 was blocked
by LCSD construction works from 3
4.4.17. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27
4.4.18.
As
per the meeting with the representative of Excelsior Hotel and World Trade
Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011.
4.4.19.
24 hours
monitoring of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on 17 November 2011, the
24 hours turbidity monitoring and was kept in November 2011. Since the
reinstating the seawall was completed on 13 January 2012 and no any water deterioration
was performed, 24 hour turbidity monitoring was then suspended on 27 January
2012.
4.4.20.
The
enhanced water quality monitoring at C6, C7, Ex-WPCWA-SW and Ex-WPCWA-SE was
commenced on 13 January 2011.
4.4.21.
Water
monitoring results measured in this reporting period are reviewed and
summarized in Table
4.15. Details of water quality
monitoring results and graphical presentation can be referred in Appendix 4.3.
Table 4.15 Summary of Water Quality Monitoring Exceedances in Reporting period
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HK/2009/01 |
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2012/08 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
P1 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 Monitoring started
on 8 Feb 2012 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started
on 29 July 2013 |
RW21-P789 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 &
HY/2010/08 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
1 |
0 |
0 |
-
WSD9
and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed
on 6 Feb 2012.
-
C8
and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.
-
C8
& C9 was temporary suspended on 30 March 2013 due to the marine works for
Contract no. HY/2009/19 had been completed on 4 March 2013
-
WSD7
and WSD20 were temporarily suspended from 27 Apr 2012
-
C2,
C3 C4e and C4w water quality monitoring station was temporarily suspended since
24 Apr 2013
-
C5e
and C5w water quality monitoring station was temporarily suspended since 29
July 2013
4.4.22.
There were 2 action level of DO and no limit level exceedance recorded
in June reporting month. Investigation found that the exceedances were not
related to Project works.
4.4.23.
No action and limit level exceedance was recorded in July reporting
month.
4.4.24.
There were no action level and 1 limit level exceedance of turbidity
recorded in August reporting month. Investigation found that the exceedance was
not related to Project works.
4.4.25.
Enhanced
DO monitoring at 4 monitoring stations in Causeway Bay Typhoon Shelter and
Ex-Public Cargo Works Area was conducted three days per week during the
reporting period. The action and limit level exceedances of water quality
monitoring are summarized in Table 4.15a.
Table 4.15a
Summary of Enhanced Dissolved Oxygen Monitoring Exceedances in
Reporting period
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA
SW |
0 |
14 |
0 |
3 |
|
Ex-WPCWA
SE |
1 |
14 |
0 |
2 |
|
Total |
1 |
28 |
0 |
5 |
4.4.26.
There were no action level exceedances and 12 limit level exceedances of
enhanced dissolved oxygen recorded in June reporting month. Investigation found
that the exceedances are not related to the Project works.
4.4.27.
There were no action level exceedances and 8 limit level exceedances of
enhanced dissolved oxygen recorded in July reporting month. Investigation found
that the exceedances are not related to the Project works.
4.4.28.
There were 1 action level exceedance and 13 limit level exceedances of
enhanced dissolved oxygen recorded in this reporting month. Investigation found
that the exceedances were not related to the Project works.
4.4.29.
Investigation
found that the exceedances are not related to the Project works. Details of graphical presentation can be
referred in Appendix 4.3.
4.4.30.
In response to the Condition 2.18 of the Environmental Permit no.
EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored. Details of additional DO monitoring results
can be referred in Appendix
4.3a.
4.4.31.
With respect to the commencement of dredging works under HK/2012/08 and
the installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since 24 July 2013
Contract no. HK/2009/01 - Wan Chai Development
Phase II – Central –Wanchai Bypass at HKCEC
4.5.1. Inert C&D waste was
disposed and non-inert C&D
waste was disposed of for the site works in this reporting period. Details of
the waste flow table are summarized in Table 4.16.
Table 4.16 Details of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
8923.65 |
62116.405 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
752 |
5856.5 |
N/A |
Non-inert C&D materials disposed, m3 |
24.22 |
1671.69 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
25850 |
203993 |
N/A |
Chemical waste disposed, kg |
NIL |
10250 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
NIL (Bulk Volume) |
97428.2 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL (Bulk Volume) |
52250 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3 – Special Treatment / Disposal contained in
Geosynthetic Containers |
NIL (Bulk
Volume) |
6773 (Bulk Volume) |
East of Cha Chau |
4.5.2. There were no Marine Sediment (Type 1 –
Open Sea Disposal) and no Marine Sediment
(Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined Marine
Disposal) disposed of in June, July and August reporting months.
Contract no. HK/2009/02 - Wan Chai Development
Phase II – Central – Wan Chai Bypass at WanChai East
4.5.3. Inert and non-inert C&D waste were disposed of for the
site works in this reporting period. Details of the waste flow table are
summarized in Table 4.17.
Table
4.17 Details of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
2577.845 |
263704.45* |
TKO137/ TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
62.31 |
1515.103 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Chemical waste disposed, kg |
1200 |
13860 |
SENT Landfill |
Marine Sediment (Type 1 – Open Sea
Disposal), m3 * |
996 |
186070 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal), m3 |
0 |
129320 (Bulk volume) |
East of Sha Chau |
*Remarks: Cumulative
Quantity of Inert C&D materials disposed and Marine Sediment (Type 1 – Open
Sea Disposal) were clarified in reporting period
4.5.4. There were Marine Sediment (Type 1 –
Open Sea Disposal) and no Marine
Sediment (Type 1- Open Sea Disposal (Dedicate Sites) & Type 2- Confined
Marine Disposal) disposed of in this reporting quarter.
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)
4.5.5. No inert and non-inert C&D waste were disposed of for the site works
in this reporting period. Details of the waste flow table are summarized in Table
4.18.
Table
4.18 Details of Waste Disposal for
Contract no. HY/2009/15
Waste Type |
Quantity this quarter |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
NIL |
65216 |
TKO137 FB |
NIL |
|
Inert C&D materials recycled, m3 |
NIL |
304 |
Ex-PCWA |
NIL |
NIL |
111.9 |
TS4 |
NIL |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
NIL |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
NIL |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
NIL |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
3280 |
103488 (Bulk Volume) |
South of Cheung Chau |
Dredging from TCBR1E /
TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
24010 |
251325 (Bulk Volume) |
East of Sha Chau |
Dredging from TCBR1E /
TCBR1W / TCBR2/ TCBR3 / TCBR4 / Maintenance dredging |
Marine Sediment (Type 3 – Special Treatment
/ Disposal contained in Geosynthetic Containers) |
3860 |
12640 (Bulk Volume) |
East of Sha Chau |
Dredging from TCBR1W /
Maintenance dredging |
Marine Sediment (Type 2 – Confined Marine
Disposal), m3 |
NIL (Bulk Volume) |
9350 (Bulk Volume) |
East of Sha Chau |
Dredging from Eastern
Breakwater of CBTS |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
NIL (Bulk Volume) |
600 (Bulk Volume) |
East Sha Chau / South
of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
Marine Sediment (Type 2– Confined Marine Disposal)
, m3 |
NIL (Bulk Volume) |
14,780 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
Marine Sediment (Type 3
– Special Treatment / Disposal contained in Geosynehetic Containers)
, m3 |
NIL (Bulk Volume) |
2,760 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
4.5.6. There was Marine Sediment (Type 1 – Open Sea
Disposal), Marine Sediment (Type 2 – Confined Marine Disposal) and Marine
Sediment (Type 3 – Special Treatment / Disposal contained in Geosynehetic
Containers) were disposed in this reporting quarter.
Contract
no. HK/2010/06 - Wan Chai Development Phase II – Central –Wanchai Bypass over
MTR Tsuen Wan Line
4.5.7. No non-inert C&D and no
Inert C&D waste were
disposed of for the site works in this reporting period. Details of the waste
flow table are summarized in Table 4.19.
Table
4.19 Details of Waste Disposal for Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
12567.88 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
267 |
HK/2009/01 |
Non-inert C&D materials disposed, m3 |
NIL |
369.48 |
SENT/TKO137SF |
Non-inert C&D materials recycled, m3 |
NIL |
60.58 |
Recyclers |
Chemical waste disposed, L |
NIL |
2600 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
NIL (Bulk Volume) |
3,891 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
NIL (Bulk Volume) |
(Bulk Volume) |
East Sha Chau |
4.5.8. There was no Marine Sediment (Type 1- Open Sea
Disposal) and no Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites)
& Type 2 – Confined Marine Disposal) were disposed in this reporting
quarter.
Contract
no. HY/2009/19 – Central- WanChai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link
4.5.9. Inert and non-inert C&D waste were disposed of
in this reporting quarter
Table 4.20 Details of Waste Disposal for Contract no. HY/2009/19
Waste Type |
Quantity this month |
Cumulative
Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
7383.94 |
355921.04 |
TM38 |
Inert C&D materials
recycled, m3 |
818.71 |
59367 |
N/A |
Non-inert C&D materials disposed, m3 |
348.32 |
1068.6 |
N/A |
Non-inert C&D materials recycled, kg |
12.32 |
333.14 |
N/A |
Chemical waste disposed, L |
0.11 |
2.12 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal), m3 |
NIL |
162 |
South Cheung Chau |
Marine Sediment (Type 2 – Confined Marine Disposal) , m3 |
NIL |
681 |
East Sha Chau |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal) , m3 |
NIL |
4976.00 |
N/A |
4.5.10. There were no marine sediments Type1- Open Sea
Disposal and there were no Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal in the reporting period.
Contract
no. HK/2012/08 –Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan
Chai West
4.5.11. Non-inert C&D waste were disposed of in this
reporting quarter. Details of the waste flow table are summarized in Table 4.21.
Table
4.21 Details of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
1247 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 * |
15 |
315 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal),
m3 * |
724 (Bulk volume) |
31759 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal) , m3 * |
330 (Bulk volume) |
108485 (Bulk volume) |
South of The Brothers (from 27 Aug 2013 onwards) |
*Remarks:
Contractor clarified the cumulative quantity of Non-inert C&D material and marine
sediment in July reporting month.
4.5.12. There were Marine Sediment (Type 1 – Open Sea
Disposal) and marine sediment Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal generated were disposed in this reporting period.
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8)
4.5.13. No Inert C&D waste and non-inert C&D waste
were disposed in this reporting period. Details of the waste flow table are
summarized in Table 4.22
Table 4.22 Details of Waste Disposal for
Contract no. HY/2010/08
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Dumping Permit (Type 1 – Open Sea Disposal) |
3270 |
16130 |
South Cheung Chau |
Dumping Permit (Type 1 – Open Sea Disposal (Dedicate Sites) & Type
2 – Confined Marine disposal) |
NIL |
17820 |
Brothers Island |
4.5.14. There were Marine Sediment (Type 1 – Open Sea
Disposal) and no marine sediment Type 1 – Open Sea Disposal (Dedicate Sites)
& Type 2 – Confined Marine Disposal generated disposed in this reporting
period.
5.0.1. The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 5.1.
5.1.1 No action and four limit level
exceedances at M6 – HK Baptist Church Henrietta Secondary School were recorded
on 5, 10, 17 and 25 June 2014 in June reporting month. The exceedances were
concluded as non-project related.
5.1.2 One limit level exceedance at M2b – Noon
Day Gun Area was recorded on 24 June 2014 in June reporting month. The exceedance
was concluded as project related.
5.1.3 No action and limit level exceedance was
recorded in July reporting month.
5.1.4 One limit level exceedance at M6 – HK
Baptist Church Henrietta Secondary School was recorded on 28 July 2014 in August
reporting month. The exceedance was concluded as non-project related
5.1.5 One limit level exceedance at M2b – Noon
Day Gun Area was recorded on 5 August 2014 in August reporting month. The
exceedance was concluded as project related.
5.1.6 Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of graphical presentation can be referred in Appendix 4.1.
5.2.1 No project related exceedances were
recorded in June, July and August 2014 reporting month at RTN2a-Hong Kong
Electric Centre during this reporting quarter.
5.2.2
Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 4.2
5.3.1 No action or limit exceedance was recorded in 1-hr
TSP and 24-hrs TSP monitoring in the June, July and August reporting period.
5.3.2 No Action and Limit Level was recorded for
odour patrol during July and August reporting months.
5.4.1.
The
summary of water quality exceedances recorded in reporting period is presented
in the Table 5.1 and Table 5.1a.
Table 5.1 Summary of Water Quality Monitoring Exceedances in
Reporting period
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
HK/2009/01 |
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HK/2012/08 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
P1 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 Monitoring started on 8 Feb 2012 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started on 29 July 2013 |
RW21-P789 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 & HY/2010/08 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
0 |
0 |
1 |
0 |
0 |
- WSD9 and
WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
- 4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed
on 6 Feb 2012.
- C8 and C9 were implemented with respect to
HY/2009/19 from 28 Jan 2012.
- C8 & C9 was temporary suspended on 30
March 2013 due to the marine works for Contract no. HY/2009/19 had been
completed on 4 March 2013
- WSD7
and WSD20 were temporary suspended since 27
5.4.2.
There were 2 action level of DO and no limit level exceedance recorded
in June reporting month. Investigation found that the exceedances were not
related to Project works.
5.4.3.
No action and limit level exceedance was recorded in July reporting
month.
5.4.4. There were no action level and 1 limit
level exceedance of turbidity recorded in August reporting month. Investigation
found that the exceedance was not related to Project works.
Table 5.1a
Summary of Enhanced Dissolved Oxygen
Monitoring Exceedances in Reporting period
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA SW |
0 |
14 |
0 |
3 |
|
Ex-WPCWA SE |
1 |
14 |
0 |
2 |
|
Total |
1 |
28 |
0 |
5 |
5.4.5. There were no action level exceedances
and 12 limit level exceedances of enhanced dissolved oxygen recorded in June
reporting month. Investigation found that the exceedances are not related to
the Project works.
5.4.6. There were no action level exceedances
and 8 limit level exceedances of enhanced dissolved oxygen recorded in July
reporting month. Investigation found that the exceedances are not related to
the Project works.
5.4.7. There were 1 action level exceedance and
13 limit level exceedances of enhanced dissolved oxygen recorded in August
reporting month. Investigation found that the exceedances are not related to
the Project works.
5.5.1. There was no non-compliance from the site audits in
the reporting period. During environmental site inspections conducted during
the reporting period, minor deficiencies were noted.
5.6.1
There was no non-compliance from the site audits in the reporting
period.
5.7.1
There was no particular action taken since no
project-related non-compliance was recorded from the site audits in the
reporting period.
6.0.1. One environmental complaint received in
June reporting month.
6.0.2. A public complaint regarding water
quality impact referred by WDII RSS team was received by ET on 12 June 2014.
Notification letter from EPD on the captioned case was subsequently received by
ET on 13 June 2014. The complainant reported that a large piece of muddy water
was found on the waterfront outside the Hong Kong Academy for Performing Arts
Theatre Block on 12 June 2014 morning.
6.0.3. ET confirmed with the Resident Site
Staff that neither marine construction works nor barge operation was conducted
at the concerned location during the time of complaint. Nevertheless, with the
respect to the EPD complaint case and the email notification issued by the
Environmental team to contractor on 12 June 2014 morning, muddy dispersion was
observe at HKCEC2W works area and the dispersion was observed partly extended
beyond the outermost layer silt curtain at 1000hrs and contractor’s immediate
follow up action was requested.
6.0.4. Mitigation measures implemented by the Contractor
for the above construction works include the deployment of double layer of silt
curtain for marine filling works area at HKCEC2W, additional silt curtain at
marine access between caisson seawall on 12 June 2014, and regular diver
checking on the silt curtain deployed at the location. It is considered that
Contractor’s mitigation measures for safeguarding the water quality during
marine filling works at the concerned location implemented would require
further review on the effectiveness to avoid seepage of muddy dispersion.
6.0.5. Follow-up inspection was further
conducted on 16 June 2014 and in addition, diver inspection check on the silt
curtain deployed was conducted by the Contractor on 14 June 2014 to confirm the
integrity of silt curtain.
6.0.6. The Contractors’ investigation report on
the complaint case was submitted to EPD via email on 18 June 2014, and the
interim report was submitted to EPD on 20 June 2014.
6.0.7. One environmental complaint under
EP-356/2009 was received in July reporting period.
6.0.8. A public complaint regarding
construction noise impact referred by RSS was received by ET on 25 July 2014.
The complainant reported that at 00:57hrs on 21 July 2014, the complainant
could not sleep due to work and machine at the project site opposite to Ngan
Tao Building, where he is staying were still going on and in operation. Noise
travelled to his flat despite it was some distance away.
6.0.9. ET confirmed with the RSS that
horizontal cutting and removal of D-wall at Eastern, Southern and Northern side
of TS2 was undertaken by Contractor of HY/2009/15 within Causeway Bay Typhoon
Shelter before 23:00 on 20 July 2014 that total 3 numbers of derrick lighter
and 3 numbers of saw cut machine were in operation, and removal of D-wall at
Panel S30A-1 of TS2 was undertaken by Contractor of HY/2009/15 within Causeway
bay Typhoon Shelter around 00:25hrs to 00:56hrs on 21 July 2014 that total 1
number of derrick lighter was in operation.
6.0.10. According to the relevant site records
under Contract HY/2009/15, before 23:00hrs on 20 July 2014, horizontal cutting
and removal of Diaphragm Wall at Eastern, Southern and Northern side of TS2 was
conducted under HY/2009/15 within Causeway Bay Typhoon Shelter. Total 3 nos. of
derrick lighter and 3 nos. of saw cut machine were in operation at the above
period. From around 00:25hrs to 00:56hrs on 21 July 2014, removal of D-wall at
Panel S30A-1 of TS2 was undertaken by Contractor of HY/2009/15 within Causeway
Bay Typhoon Shelter. Total 1 no. of derrick lighter was found operating at the
above period.
6.0.11. After reviewing the relevant records and
information verified by RSS and the Construction Noise Permit (CNP) no.
GW-RS0592-14, it was considered the condition of CNP GW-RS0592-14 was not
fulfilled by the Contractor of HY/2009/15. “From 00:25hrs to 00:57hrs on 21 July 2014, the
PME(s) (1 no. of Derrick Lighter) on-site could not follow with any given PME
grouping requirement(s) as stated in condition 3.a. and condition 3.d. in no.
GW-RS0592-14.” According
to the site recorded provided by the RSS, the derrick lighter was found
malfunction at around 23:00hrs on 20 July 2014 while the diaphragm wall cutting
procedure was incomplete. Under safety and navigation considerations, the
completion of diaphragm wall removal was necessary and of imminent need.
6.0.12. The contractor of HY/2009/15 was advised
to review the construction sequence and emergency response procedure for
construction activities during restricted hours and night time period to allow
for sufficient buffer time for work completion such that the Construction Noise
Permit would be strictly followed. Furthermore, the Contractor of HY/2009/15
was suggested to conduct throughout checking of PME used on site prior to work
commencement to minimize the potential malfunctioning of PME during the course
of work which affect the duration of works.
6.0.13. No environmental complaint was received
in August reporting month.
6.0.14.
The details of cumulative complaint
log and summary of complaints are presented in Appendix 6.1.
6.0.15. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works
(Mar 2010) to last reporting period |
28 |
June 2014- August 2014 |
2 |
Project-to-Date |
30 |
Table 6.2 Cumulative Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1. According
to Condition 3.4 of the EP-356/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III, Central-Wanchai Bypass
and Island Eastern Corridor Link projects.
7.0.2. According
to the Final EM&A Report of Central Reclamation Phase III (CRIII) for
Contract HK 12/02, the major construction activities were completed by end of
January 2014 and no construction activities were undertaken thereafter and the
water quality monitoring was completed in October 2011 and no Project-related exceedance
was recorded for air and noise monitoring.
It can be concluded that cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area, Diaphragm wall construction and pipe pile wall construction were
performed in August 2014 reporting month. As no project related exceedance were
recorded during the reporting period, cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was considered as insignificant.
7.0.4.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai Development
Phase II were marine works at HKCEC areas, tunnel works at Wan Chai East and
filling works at Wan Chai West. The major construction activities under Central-Wan
Chai Bypass and Island Eastern Corridor Link Projects were bridge construction
and tunnel works at Central Interchange, land base bored pilling works at
Victoria Park Road and ELS, segment launching works and tunnel works at North
Point area. The major environmental impact was water quality impact at Causeway
Bay and Wan Chai. Marine-based construction activities were filling works at
WanChai West and removal of temporary reclamation at TS4, TS2 and EX-PCWA at
Wan Chai East in the reporting month.
7.0.5. No significant
air impact from construction activities was anticipated in the reporting month.
Besides, project related exceedances were recorded during the air and noise environmental
monitoring events in June and August reporting months were rectified. Thus, it
is evaluated that the cumulative construction impact from the concurrent
projects including Central Reclamation Phase III (CRIII), Wan Chai Development
Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link
projects (IECL) was insignificant.
8.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
8.0.2. No non-compliance was noted and no prosecution was
received during the reporting period.
8.0.3. The construction programmes
of individual contracts are provided in Appendix 8.1.